Wuyang new steel plate Co., LTD. Tempering heat treatment production line project completion environmental protection self-acceptance publicity

Time:

2022-08-24


Wuyang new steel plate Co., LTD. Tempering heat treatment production line project completion environmental protection self-acceptance publicity

Wuyang new steel plate Co., LTD. Tempering heat treatment production line project completion environmental protection self-acceptance publicity

Construction project Name: Tempering heat treatment production line Project

Construction project address: North of Lihuizhuang, West section of Hubin Avenue, Wugang City, in the existing second rolling mill house

Name of construction unit: Wuyang New Kuanhou Steel Plate Co., LTD

Nature of construction project: reconstruction and expansion

Construction scale: Heat treated steel plate 160,000 t/a

Main construction contents: add 1 thermal insulation pit, 2# heat treatment furnace to extend the roller table, add 1 open fire heating roller bottom heat treatment furnace (4# heat treatment furnace) and its supporting loading roller table, remove the original 1#-5# cold bed, and build a new steel drying platform in 1#, 2#, 3# and 5# cold bed areas.

Eia document preparation unit: Henan Metallurgical Research Institute Co., LTD

Eia document approval department: Wugang Environmental Protection Bureau

Document approval number: Dance Ring Table [2019]010

Document approval time: July 1, 2019

Project start time: July 2019

Completion date: April 27, 2022

Actual total investment: 87.5 million yuan

Actual investment in environmental protection: 1.005 million

Proportion of investment in environmental protection: 1.15%

Acceptance Announcement states:

On July 4, 2022, Wuyang New Kuanhou Steel Plate Co., Ltd. organized experts, according to the "Wuyang new Kuanhou Steel Plate Co., Ltd. tempering heat treatment production line engineering environmental protection acceptance monitoring report form", and the "Construction project completion environmental protection acceptance Interim Measures", Strictly in accordance with the relevant state laws and regulations, construction project completion environmental protection acceptance specification, this project environmental impact assessment report and approval department for examination and approval opinions for tempering heat treatment production line project in the independent completion acceptance of environmental protection, through inspection and discussion, participants agree to the project through completion acceptance of environmental protection, And issue the construction project completion environmental protection acceptance opinions.

According to the Decision of The State Council on Amending the Regulations on the Management of Environmental Protection for Construction Projects (Order No. 682 of The State Council) and the Announcement of the Ministry of Environmental Protection on the Issuance of the Interim Measures for the Acceptance of Environmental Protection for Construction Projects (State Environmental Assessment [2017] No. 4), Now Wuyang new steel plate Co., LTD. Tempered heat treatment production line engineering environmental protection acceptance monitoring report form for acceptance publicity, the publicity period is 20 working days from now on, if you have comments and suggestions, please contact Wuyang new steel plate Co., LTD.

Previous

Next

Love female workers warm half the sky

In order to care for the physical and mental health of female workers, and further do a good job of union service and care for female workers, since late September, Hegang Wugang union carried out the "your health I care" female workers care action, the organization of the company's 20 units of more than 5100 (including retirement) female workers for health examination.

Set up the stage of innovation to fill the driving force of enterprise development

Economic globalization makes enterprises face the fierce competition from the global market, and this competition is the competition of talents in the final analysis. It has become an important magic weapon for enterprises to cultivate core competitiveness to train the talents of relevant positions in a planned way.

General rules for students of Wugang of Hegang Group

Wugang Company of Hegang Group is the first production and scientific research base of broad and thick steel plates in China, which is the important substitution base of domestic import of broad and thick steel plates, located in Wugang city, Pingdingshan city of Henan province.

Wuyang new steel plate Co., LTD. Tempering heat treatment production line project completion environmental protection self-acceptance publicity

Wuyang new steel plate Co., LTD. Tempering heat treatment production line project completion environmental protection self-acceptance publicity

Coagulation and cohesion to jointly fight against the epidemic

In the summer of 2022, COVID-19 outbreaks spread across many parts of the country, putting medical workers once again at the forefront of the fight against the epidemic. Fight the heat, fight tired, give up the small home, for everyone, where there is a need to go to where

Hegang Wugang Party Committee for workers and workers masses to do practical things

Design and use new step ladder. Starting from the details, the Party Committee of the Ministry of Transport arranged specials to count the dining intentions of the workers on duty in the two steel plate storage and transportation areas every day, and sent lunch and dinner to the posts